With the advent of the global Covid-19 pandemic in 2019/20 and a surge in hospital admissions, the Gauteng Health Department and the Gauteng Department of Infrastructure Development (GDID) embarked on a project to increase its Intensive Care Unit (ICU) capacity through a national refurbishment and additional build programme. As such, Enza Construction (Pty) Ltd was commissioned to construct the Bara500 C- 19 hospital facility and was responsible for the design, construction and commissioning of the Hospital Facility consisting of 500 ICU units on a turnkey basis at the Chris Hani Baragwanath Hospital. Enza Construction (Pty) Ltd contracted Mace Project Solutions, MMQS Mace Consultancy, Ruben Reddy Architects, CKR Engineers and Gibb to perform the required design services.

Timelapse SA was there to capture the construction every step of the way. With one camera set-up outside then moved to a different angle and later moved indoors, this was the first project where we captured everything happening inside and out. From earthworks, concrete and steelworks until fixing beds and basins, we captured it all!

To expedite the building process, Alternate Building Technology (ABT) was used. This entailed the use of light steel frame construction which allowed for significant reduction in time for construction, in comparison to conventional building methods. The Chris Hani Baragwanath Hospital in the Soweto area, south of Johannesburg, is the largest hospital in Africa and third largest hospital in the world. It boasts 6,760 staff members, 3,900 beds and occupies approximately 70 ha.

Start Date: 3rd July 2020

Finish Date: 12th Feb 2021

Total Duration: 30 weeks

Overall Construction site area: 51000m2

Bulk earthworks duration: 6 weeks

Bulk earthworks cut to stockpile: 35000m3

Additional rock drilling, blasting and removal of: 28000m3

Fill material used to create the hospital platforms: 54000m3

Retaining walls: 350m of average 4,5m high

no. earthmoving plant vehicles during peak of Earthworks operations: 46

Concrete used: 4685m3

Alternative Building Technology (ABT) wall systems erected: 16 925m2

Hospital space under roof – 26650m2

Number of beds – 505 (500 ICU + 5 Admissions)

Number of clusters – (20 Clusters, each with 25 ICU beds)

Time to convert one 25 bed cluster from enclosed grey box to complete product– (5 weeks)

24 hours, 6,5 days per week construction period

Peak amount of people on the site within a 24 hour cycle – 983

Manhours worked over a 7 month period – 1 126 383 manhours

Local job opportunities created over the construction period – 546

Local SMME contractors employed and empowered – 44

CREDITS:

Produced by: The Construction Timelapse Company

Directed by: Joe Louw / Jonelle Louw

DP: Joe Louw

Offline editing & grading: Jonelle Louw / Jennifer Pillinger

Online editing & Graphics: Nanette Dreyer – Handmade Media